SEZ Alabuga highest level in electric power supply reliability

8 December 2014, Monday
On 8 December 2014, SEZ Alabuga hosted a ceremony of launching a new distribution substation with 600 megawatt capacity. The official ceremony was attended by the President of the Republic of Tatarstan Rustam Minnikhanov, the Tatarstan Deputy Prime Minister and Minister of Industry and Trade Ravil Zaripov, as well as executives and SEZ Alabuga resident companies.
A substation is fully automated; only two mechanics can operate the facility at the same time. The total cost of the distribution substation is RUB 1.5 bln.