Kazan DSK implemented productivity increase programme on Sommer line

1 June 2021, Tuesday

Kazan DSK, one of the largest enterprises in Tatarstan producing prefabricated house sets for the construction of multi-storey large-panel houses, entered a programme of the Labour Productivity national project in June 2019.

The programme “Improving Productivity in the Production of Reinforced Concrete Slabs on the Sommer Circulation Line” was implemented here as a pilot project with the participation of the Federal Competence Centre (FCC).

The first step in implementing the programme was the setting up of a project team at the plant which optimised the processes at the pilot stream under the watchful eye of FCC specialists.

In parallel to the optimisation processes which have been initiated, managers were trained in the decomposition of objectives: the work of the entire company was broken down into its individual components and each objective was considered separately. Certification of internal trainers was also carried out at the plant, who then independently trained specialists and heads of individual working teams.

The Labour Productivity and Employment Support national project was approved by Russian President Vladimir Putin in 2018 and is intended to create conditions for continuous growth in country’s labour productivity. To implement the tasks set, the Russian Government initiated a package of measures to support businesses.